effort estimate

noun

A reasoned forecast of the working time needed to carry out agreed activities.

The effort estimate includes a range because documentation for the external integration is still missing.

An effort estimate starts by breaking work into parts that can be discussed. For each part, the team estimates the work involved and records assumptions, dependencies and uncertainties. The total supports decisions about budget and scope.

Effort is not elapsed time

Forty hours of work does not automatically mean something will be ready on Friday. Waiting for access, feedback or an external supplier can extend the calendar schedule. Conversely, some activities can run in parallel.

State which unit is being used and which activities are included. Alongside programming, consider testing, meetings and delivery.

An estimate can change

New information may increase or reduce the estimate. A range makes uncertainty visible, for example when an existing Glossary · In briefcodebaseA codebase is the collection of source code used to build and maintain a software product or component.Read more⁠ still needs to be examined. An effort estimate is not, by itself, a fixed-price agreement. Project agreements should explain how deviations are discussed and charged.